Important Events

S.No Description Date
1 Project Allotted by GoN 04.02.2021
2 Signing of Memorandum of Understanding (MoU) with GoN 11.07.2021
3 Vetting of Detailed Project Report (DPR) by IBN, GoN 31.03.2022
4 Appraisal of DPR by Central Electricity Authority (CEA), Gol 31.10.2022
5 Incorporation & Registration of SJVN Lower Arun Power Development Company (SLPDC) 26.05.2023
6 Investment Approval by Public Investment Board (PIB) of Gol 30.05.2023
7 Signing of Project Development Agreement (PDA) between SLPDC and IBN, GoN 01.06.2023
8 Approval of Supplementary Environment Impact Assessment (SEIA) 31.10.2023